WORK AT HEIGHT: AVOIDING FALLS THROUGH FLOOR OPENINGS

HSE prosecution highlights the consequences of inadequate planning, protection and supervision on a construction site.

HSE PROSECUTIONCOURT OUTCOMEADDITIONAL COSTS
21 September 2026£300,000 fine£9,284.05

The case in brief.....

A recent Health and Safety Executive (HSE) prosecution provides a stark reminder that floor and stairwell openings must be treated as significant fall hazards throughout construction. In January 2024, 24-year-old labourer Joseph Tuck fell through an unprotected stairwell opening at a development of four new homes in Sowerby Bridge. He suffered serious spinal injuries and has not returned to physical work.

What happened?

  • The incident occurred while four new domestic dwellings were being constructed by Hillbeck Homes (Sowerby Bridge) Ltd.
  • Mr Tuck was working as a temporary labourer for a scaffolding company and was in his second week on the job.
  • He stepped backwards and fell one storey onto concrete through an opening intended for a staircase that had not yet been installed.
  • The opening was not securely covered. Previous loose scaffold boards had been removed and the open edges were not protected.
  • Following the fall, Mr Tuck was unconscious and required rescue by West Yorkshire Fire & Rescue and the HART team.
  • HSE found failures in the planning and supervision of work at height and in the measures provided to prevent a fall.
COURT OUTCOME
Hillbeck Homes (Sowerby Bridge) Ltd was found guilty on three charges. The company was fined £300,000 and ordered to pay £9,284.05 in costs at Leeds Magistrates’ Court on 16 September 2026.

The key lesson for construction projects

An opening in a floor is a foreseeable fall hazard, even when the final staircase, platform or other permanent feature has not yet been installed. The temporary condition of the site does not remove the need for suitable protection. Controls need to be planned before the activity starts and maintained as the work progresses.

In practical terms, this means asking:

✓ Has every floor, stairwell, shaft, roof and service opening been identified?

✓ Is each opening securely covered or physically protected against falls?

✓ Are temporary covers suitable, secured and capable of remaining effective during the work?

✓ Is edge protection provided where a fall could occur?

✓ Have workers and subcontractors been told about the hazards and the controls that must remain in place?

✓ Are site inspections and supervision checking that controls have not been removed, bypassed or deteriorated?


What does Safety Advisors advise?

Plan the task

Identify openings and fall risks before work starts.

 

Assess the risk

Use a task-specific assessment and review it when conditions change.

 

Prevent the fall

Use secure covers, guardrails, working platforms or other suitable collective controls.

 

Supervise and inspect

Make sure controls remain in place and workers know what is required.

 

What does HSE guidance say?

HSE guidance on work at height states that activities must be properly planned, appropriately supervised and carried out by competent people. The risks should be assessed and suitable equipment and control measures selected. The hierarchy of control places emphasis on avoiding work at height where reasonably practicable, then preventing falls, and finally reducing the distance and consequences of a fall where the risk cannot be eliminated.

For construction work, the Work at Height Regulations 2005 are particularly relevant. HSE – Working at height: A brief guide provides practical guidance on the management of fall risks, including falls into floor openings.

Safety Advisors – what we recommend

This case demonstrates why work-at-height controls should be considered as part of the overall construction management system rather than as a last-minute site issue. A robust approach should include suitable planning, risk assessment, method statements where appropriate, competent supervision, clear site arrangements and routine inspection of temporary protection.

PLANPROTECTCHECK
Identify openings during planning and review the risk as the build sequence changes.Use secure covers, guardrails, working platforms or other suitable collective controls.Inspect protection regularly and after changes to the work area. Act immediately if controls are missing.

Need support with construction health & safety? Safety Advisors can provide practical advice, site inspections, risk management support and competent H&S consultancy tailored to your project.

Find out more: safetyadvisors.co.uk


Source and editorial note

This newsletter is an edited and independently written summary of an HSE prosecution published on 21 September 2026. It is intended for general information and should not be treated as legal advice. Read the original HSE press release. The illustrative graphics in this document were created by Safety Advisors for this newsletter.